Edo NEWMAP became effective on September 16, 2013 and has so far carried out the following activities:

  1. Commissioned Consultants for detailed engineering designs for the three prioritized sites in the state.
  2. As part of due diligence, the SPMU engaged consultants to conduct environmental and social assessment studies in the sites as well as Resettlement Action Plans (RAPs).
  3. Edo NEWMAP registered 9 Community Associations and constituted 3 sites committees in the project affected areas in readiness for implementation.

Identification and preparation of environmental safeguard instruments for all three sites in progress All three sites are registered with the EA Department of the Federal Ministry of Environment.

Award of contract for Reclamation, Channeling and Remediation works at Ekehuan Road Gully/West Moat Flood and Gully Erosion catchment area in Benin City, Edo State – Phase. 

Advertisement of Procurement of Works at Queen Ede Gully Erosion Site.

Advertisement of Procurement of Contractor for the Construction of Reclamation, Channelling and Remediation Works at Oshiobugie Flood and Gully Erosion Sites at Auchi.